The Trans Mountain expansion project would triple the capacity of the existing pipeline between Edmonton and a shipping terminal in Burnaby, B.C. (Canadian Press file images)

Trans Mountain pipeline expansion cost jumps 70% to $12.6 billion

The estimate of $7.4 billion was made in 2017 by the previous owner

The cost to build the Trans Mountain pipeline expansion has jumped by 70 per cent to $12.6 billion from a three-year-old estimate of $7.4 billion.

President and CEO Ian Anderson says the company owned by the federal government has spent $2.5 billion to date, including the impact of delays and additional regulatory processes, leaving an additional $8.4 billion needed to complete the project, plus $1.7 billion of financial carrying costs.

He says the project is now expected to be in service by December 2022.

The estimate of $7.4 billion was made in 2017 by the previous owner, Houston-based Kinder Morgan, Inc., which sold the expansion project and the existing pipeline to the federal government in 2018 for $4.5 billion.

Opponents have attacked the greenhouse gas emission and oil spill risks of the pipeline project but they’ve also charged it will be a money-loser with unproved markets in Asia that will fail financially and leave the public holding the bag.

ALSO READ: Opponents in B.C. to ramp up protests against Trans Mountain pipeline

Anderson says the company is recommending that Ottawa, as owner and lender, set aside a further $600 million reserve for cost impacts beyond the control of Trans Mountain.

Opponents of the pipeline expansion have vowed to do whatever it takes to stop the project despite losing a legal challenge before the Federal Court of Appeal earlier this week.

The four First Nations who lost the court challenge on Tuesday have 60 days to seek leave to appeal to the Supreme Court of Canada.

The expansion project would triple the capacity of the existing pipeline between Edmonton and a shipping terminal in Burnaby, B.C.

The Canadian Press

Like us on Facebook and follow us on Twitter.

Trans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Comments are closed

Just Posted

One of the unsung heroes that make Clearwater tick

“She is a networker and she knows how to build a great team.”

Severe thunderstorm watch in effect for Cariboo, North Thompson region

Prince George, Quesnel, Williams Lake and 100 Mile House all under watch

Community Foundation wants charities to apply for emergency funding

The $350 million emergency funding was created to help vulnerable populations during COVID-19

Back in Time

Historical Perspective

High water and flooding hits Clearwater

Potential for roadblock on Clearwater Valley Road due to potential washouts

The pandemic is widening Canada’s workplace gender gap

Gender pay gap is incentivizing fathers to work while mothers watch children, a new B.C. study has found

3 people dead in Prince George motel fire

Fire personnel believe the blaze was suspicious although investigation in early stages

B.C. sets terms to review police, mental health, race relations

MLAs to recommend Police Act changes by May 2021

Feds announce $8.3M to deal with ‘ghost’ fishing gear in B.C. waters

Ghost gear accounts for up to 70 per cent of all macro-plastics in the ocean by weight

Almost 99% less land in B.C. burned this year compared to 2018

2018 was the worst year on record for wildfires

B.C. orders Coastal GasLink to stop pipeline construction near protected wetlands

The 670-kilometre pipeline is planned to transport natural gas from northeast B.C. to Kitimat

Sunflower Highway, art initiative to connect Fraser Valley, Thompson-Nicola and Okanagan

Sunflowers made out of reclaimed materials will be installed on public art trails

B.C. tent camps persist as hotels, housing bought for homeless

Current estimate 40 camps, homeless counts stalled by COVID-19

Most Read