Trans Mountain gets ready for B.C. pipeline installation

North Thompson line, Burnaby terminal work scheduled

Twinning the B.C. section of the Trans Mountain pipeline will begin in the North Thompson by this fall, the company says in its latest six-month work schedule filed to the National Energy Board.

Work is underway along the entire line from Edmonton to Burnaby to set up temporary construction yards and camps with worker accommodation and construction offices, as well as pipe stockpile sites in Valemount, Blue River, Clearwater, Merritt and Hope.

Work is scheduled to begin in September to clear and survey a 120 km section of pipeline route between Mt. Robson Provincial Park and Blue River, connecting to a longer section between Edmonton and Jasper National Park in Alberta.

Work includes wildlife surveys, weed control and relocation of rare plants to comply with the 157 conditions required by the NEB and a further 37 conditions in the B.C. government’s environmental certificate. Despite federal and provincial approvals and what the company calls “unprecedented scrutiny,” the project continues to be dogged by orchestrated protests.

RELATED: Trans Mountain: The economics of oil

RELATED: Simpcw First Nation patrols pumping stations

RELATED: Oil by rail rises in B.C. as pipeline battled

Spending on the project has resumed after Prime Minister Justin Trudeau announced in May the federal government is buying the project assets for $4.5 billion, to ensure the twinning of the 65-year-old pipeline that delivers synthetic heavy crude and refined fuels from the Alberta oil sands to B.C. and Washington state refineries.

Kinder Morgan Canada negotiated the sale after setting a deadline of late May to have assurances that the project would proceed without interference from the B.C. government.

Work continues this summer on expansion of the Sumas terminal at Abbotsford, Burnaby terminal and Westridge marine terminal, which includes a tunnel through a portion of Burnaby Mountain.

more to come…

Just Posted

TLC hits 81 per cent of fundraising goal

Group aims to protect Clearwater ancient swamp and wildlife corridor

Check out the display

Smith residence ready for spectators

Mike Wiegele kicks off 50th anniversary season

Operation ready to embark on the festivities throughout the next four months

Vavenby weekly news update

Danish couple visiting Vavenby want to make Canada home

Back in Time

Historical Perspective

B.C. woman charged in connection to stolen vehicle smash-up in Kamloops

Kersten Ina Peters was arrested in the Fraser Valley on Friday, Dec. 6

Tavares scores twice as Maple Leafs earn 4-1 win over Canucks

Vancouver sees two-game win streak snapped

UPDATED: No survivors in Gabriola Island plane crash: RCMP

Coroner confirms multiple fatalities after small plane goes down Tuesday night near Nanaimo

VIDEO: Harbour Air makes history with first electric aircraft test flight

Successful flight marks first of its kind in the world

The Grinch who Stole a Hedge: Security camera captures Chilliwack tree theft

RCMP arrives as person calmly walks away with tree in downtown area

Salmonella outbreak in Canada linked to rodents and snakes

92 cases of salmonella across six provinces, including B.C.

Meng Wanzhou wins right to more documents involving arrest at Vancouver airport

Defence lawyers allege the Huawei executive was unlawfully detained, searched and interrogated

Toronto Raptors, Don Cherry top the list of Canadians’ Google searches in 2019

‘Champions’ was the theme of the last year, Google said

B.C. patients wait 41% longer than national average to see a walk-in doctor: Medimap

The longest wait time was found in Sidney, B.C., where patients waited an average of 180 minutes

Most Read