Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Just Posted

UPDATE: Missing senior couple found

A senior couple from the Lower Mainland have been reported missing

Clearwater RCMP weekly police report

Clearwater RCMP responded to 41 calls for service over this past week

Editor, The Times:

Proportional Representation Debate?

Hospice campaign goes into seventh year

Lights to Remember raises funds for needed training of Hospice members

Trudeau offers to help Pacific islands face climate change impact

Prime Minister Justin Trudeau met with the leaders from the Pacific island nations on Saturday during the APEC Summit in Papua New Guinea

Price makes 36 saves as Habs edge Canucks 3-2

Late goal lifts Montreal past Vancouver

BC Minister of Agriculture loses stepson to accidental overdose

Lana Popham announces death of her 23-year-old stepson, Dan Sealey

Canadian military’s template for perfect recruits outdated: Vance

Gen. Jonathan Vance, the chief of defence staff says that the military has to change because the very nature of warfare is changing, particularly when it comes to cyber-warfare

‘Toxic’ chosen as the Word of the Year by Oxford Dictionaries

Other top contenders for 2018 include ‘gaslighting’ and ‘techlash’

RCMP bust illegal B.C. cannabis lab

Marijuana may be legal but altering it using chemicals violates the Cannabis Act

Canada defeats Germany 29-10 in repechage, moves step closer to Rugby World Cup

Hong Kong needs a bonus-point win over Canada — scoring four or more tries — while denying the Canadians a bonus point

Avalanche Canada in desperate need of funding

The organization provides avalanche forecasting for an area larger than the United Kingdom

Quesnel fed up with detour, urges Ottawa to speed up road repair

West Fraser Road has been on detour since spring 2018, with no plans to repair washout until 2020

Most Read